By providing your contact information to Kelly Henderson, your personal information will be processed in accordance with Kelly Henderson's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Kelly Henderson in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Kelly Henderson at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.

Thank you for your message. I will be in touch with you shortly.

Two-story brick house with a stone walkway across the lawn and a large mature tree.

The Route From Tanglewood to Memorial Park Is Being Rebuilt at Bayou Level

"This project will install a safe hike-and-bike bridge over the [Buffalo] Bayou, connecting existing trails and infrastructure," Houston City Council member Joe Panzarella said in June, shortly before council unanimously approved the West Loop Shared Use Pathway and Bridge. The key word in that sentence is "bayou." Most coverage described the project as a bridge across Loop 610. According to Uptown's own project documents, the new span will cross Buffalo Bayou, and the path will pass under the West Loop bridges at water level.

For Tanglewood, that detail decides which way the new link will run. It also explains why the link is taking so long. The western edge of Memorial Park, the side nearest Tanglewood, is under construction at the same time. A Tanglewood resident's walking or riding route to the park will change on both ends over roughly the same period, and neither end has settled yet.

Where the route starts today

The neighborhood already has a good stretch of trail of its own. The Tanglewood Esplanade is a wide, crushed-rock path along the Tanglewood Boulevard median, shaded by the trees overhead, with bike lanes on both sides of the boulevard. It's a calm, enclosed loop. Going farther means leaving the median for regular streets.

The Houston Parks Board publishes a bike route that shows what happens next. Riders follow streets and sidewalks through Tanglewood, pass under Loop 610 at Woodway, then continue along Woodway and Memorial Drive. They don't reach the Buffalo Bayou Trail until after crossing Shepherd. Today, that freeway underpass is the main way across without a car.

How the Woodway crossing feels has been reported before. In 2021, the Houston Chronicle called the intersections on the west side of Loop 610 at Woodway and Memorial chaotic for walkers and cyclists and singled out the Woodway corner and underpass as poor. That article is five years old, and conditions may have changed since. Still, it's the clearest public description of the problem the new project is meant to solve.

What the new path actually follows

Uptown's request for qualifications divides the route into five segments. In order, the path:

  1. Starts near Hollyhurst and Uptown Park and follows Post Oak and the West Loop south to Buffalo Bayou.
  2. Crosses the bayou on a suspension bridge with 14 feet of clear width.
  3. Passes under the West Loop bridges on a separately lit shared-use path.
  4. Winds through Memorial Park's Old Archery Range and the Houston Arboretum to Woodway.
  5. Crosses Woodway and Memorial Drive and connects to the existing shared-use path on North Post Oak Road.

From Tanglewood's point of view, the route replaces the street-level underpass with a protected corridor along the water and through the trees. It doesn't bring a trail into the neighborhood itself. The closest connection points are along Post Oak and at the North Post Oak Road end, so Tanglewood residents will still reach the trail on the streets they use now. What changes is the hardest part of the trip, getting under the freeway.

Uptown already has the sidewalks that would feed the path. The district describes more than 25 miles of widened sidewalks and urban-trail connections toward Memorial Park. Along Post Oak Boulevard, the sidewalks were widened to 12 feet as part of the Boulevard Project. In a July 2025 interview, Clark Martinson, Uptown Houston's public spaces director, said the project begins at the corner of Post Oak Boulevard and Uptown Park Boulevard.

Why there is still no opening date

The project's money and contractors have been in place for a while. Its estimated finish date has moved with each new document:

Date Document Schedule stated
January 29, 2024 Uptown architect RFQ Construction to begin in the middle of calendar year 2025
July 22, 2025 Interview with Uptown's Clark Martinson Construction slated for the fourth quarter of 2025, finished by early 2027
September 2025 Uptown construction-inspection RFQ SWA and Consor named for construction administration, Forney Construction as construction manager at risk
September 24, 2025 District board minutes FTA reimbursements received, upcoming schedule presented to the board
June 17, 2026 City Council ordinance No construction or completion timeline given
September 23, 2026 Harris County Improvement District #1 agenda TxDOT advance funding agreement listed for consideration

The cost estimate also went up. The earlier RFQ listed a $21 million construction budget. In June 2026, Houston Public Media reported an estimated total of about $22.5 million, funded by grants from the Federal Transit Administration and the U.S. Department of Housing and Urban Development, with no city funding required. A Houston Chronicle report on the approval likewise said the city had not given dates for when construction could start or finish.

The bayou-level design helps explain the latest agenda item. A path under the West Loop bridges sits on Texas Department of Transportation right-of-way. On September 23, the Harris County Improvement District #1 board was scheduled to consider a resolution to enter an advance funding agreement with TxDOT for "the Uptown Memorial Park Trail and Bridge Project and Buffalo Bayou Flood Remediation on TxDOT Right-Of-Way," along with a separate development agreement with the Uptown Development Authority. An agenda item isn't an approval, and as of today the minutes from that meeting haven't been published. The most accurate status is this: the project is approved and funded, and the agreements it depends on are still moving forward.

The park's west side is changing too

At the other end of the walk, Memorial Park is rebuilding the area closest to Tanglewood. Construction on Memorial Groves began in spring 2026 along the West Memorial Loop Drive corridor, and completion is scheduled for late 2027. The Memorial Park Conservancy says the western segment of the Outer Loop Trail will stay closed until 2027 during that work.

Seymour Lieberman Trail runners will also see changes. As part of Memorial Groves, about 0.7 miles of the trail will move farther from West Memorial Loop Drive so that trees can be planted between the trail and the road. Grassy areas and new fitness stations are planned along that stretch. The full trail runs 3.02 miles and is for pedestrians only. Land Bridge and Prairie paths connect it to the South Land Bridge Trail.

Riders have a different set of trails. Bikes aren't allowed on the Seymour Lieberman Trail or the Cullen Timing Track. The Conservancy lists two multi-use options: the 1.92-mile Commuter Trail along Memorial Drive and the 2.34-mile Outer Loop Trail around Memorial Loop Drive. With the Outer Loop's western segment closed, a cyclist coming from Tanglewood has fewer park trails available right now on the side they arrive from.

That overlap shapes the next year. The new bridge connects to trails through the Old Archery Range and the Arboretum, which sit on the same west side of the park where Memorial Groves construction is underway. Both projects point to the same result, a greener and easier route between Tanglewood's streets and the park's trails. Neither has finished.

What the route looks like this fall

The Woodway underpass is still the way in for now. The next big event in the park is the Bayou City Art Festival, which runs October 9 through 11, 2026, from 10 a.m. to 6 p.m. each day. General parking is at Delmar Stadium, with a $12 day pass and a shuttle to the festival entrance.

For everyday runs and rides, the Tanglewood Esplanade remains the shaded part of the trip that's already finished. Past it, runners can head for the Seymour Lieberman Trail and riders for the Commuter Trail, keeping in mind that the western Outer Loop is closed until 2027.

The next real milestone for the bridge is a vote. Once the Harris County Improvement District #1 minutes show action on the TxDOT advance funding agreement, the project will have cleared the agreement its under-freeway segment depends on. A construction date would have to come after that.

I follow projects like the Uptown Memorial Park Trail and Bridge because they change how a neighborhood's streets get used long before they appear in any listing. If you live in Tanglewood and want to talk through how the trail, the Memorial Groves work, or the latest Uptown changes affect your own home, Kelly Henderson would be glad to share what she's watching. Let's Connect.